Beitbridge fire station almost complete

Thupeyo Muleya

The construction of a new fire station which is part of the US$300 million Beitbridge modernisation project is nearing completion, an official has said.

The fire station, an animal quarantine, sewer oxidation dam, a landfill, roads upgrading, construction of 220 staff houses, and a 11,4 megalitres water reservoir are some of the out-of-port facilities under construction.

The Government and the Zimborders Consortium are implementing the massive infrastructure development initiative on a 17-and-half-year Build Operate and Transfer (BOT) concession.

Zimborders Consortium’s General Manager, Mr Nqobile Ncube said the fire station will address the perennial fire and emergences rescue services deficiencies in the border town.

He said the project will be completed in the next five months.

Related Posts

COMMENT: IMF review shows economic reforms bearing fruit

ZIMBABWE’s improving economic performance, low inflation, stability of exchange rates and many other reforms have been given the thumbs-up by the International Monetary Fund in its first review of the…

State-led capital key to wooing private infrastructure funding

Martin Kadzere THE Government should capitalise national development finance institutions and take full responsibility for financing critical infrastructure to crowd in private capital and bridge critical funding gaps across Special…

Leave a Reply

Your email address will not be published. Required fields are marked *

×