The Zimbabwe Diamond Technology Centre (Pvt) Ltd (ZDTC) is challenging a High Court judgment compelling it to pay $4,3 million plus interest to seven construction firms that were involved in the construction of the giant diamond cutting and polishing structure in Mt Hampden. The seven companies — Kenmark Builders, Studio Arts Incorporated, NMC Consulting Engineers, Craft View Consultants, Vanguard Engineering Services, Ncube Burrow, Astra Steel and Engineering — sued ZDTC for varying amounts depending on the services they provided.

Failure or refusal by ZDTC to pay for the services prompted the group of engineering firms to jointly file a combined $4,3 million law suit at the High Court in 2011. High Court judge Justice Mary Dube heard the arguments by all the parties involved and ruled in favour of the group of construction companies.

She found that the firms had succeeded in proving their claim before ordering ZDTC to pay Kenmark its outstanding $1 623 954. Justice Dube said Studio Arts was entitled to $1 011 683 for the services rendered while she ordered that Mazuva should get $593 254.

Craftview was awarded $404 987 while Vanguard got an order for the payment of $442 199. Ncube Burrow will get $263 161 while Astra was awarded $51 837.

In a notice of appeal filed by Manase and Manase Legal Practitioners at the Supreme Court recently, ZDTC argued that the judge Justice Dube erred in awarding Kenmark $1,6 million in the absence of any written agreement between the parties. It was ZDTC’s argument that the figures claimed by the plaintiffs were unilateral and unreasonably high. The fees, according to ZDTC, were too high and they amounted to extortion.

ZDTC argued that the court erred in holding that Studio Arts claim was legitimate when it came out in the trial that it was based on the lesser budget of $4 million agreed by the parties and not the claimed $24 million budget.

The company argued that Crafts View Consultants had abandoned the project and another company took over, but the court erred in awarding its claim. The appeal is yet to be set down for hearing at the Supreme Court.

The companies worked on the project before being elbowed out without payment. Their claim was based on the services rendered and the materials supplied for the project. According to court documents, ZDTC entered into agreements with each of the plaintiffs between January and July 2010 to provide services in the construction of the centre.

Such services ranged from the actual construction, architectural services, consulting and structural engineering, quantity surveying to mechanical and electrical engineering as well as the provision of reinforcement steel. ZDTC, in its plea, accepted that it entered into separate agreements with all the consultants, except Kenmark. It was argued that the claims were unbudgeted for and were not based on actual work done. However, the court held that the seven companies had proved their case and that they must be paid.

Related Posts

Mega Market moves to snap up Lobels in bid to dominate food value chain

Nelson Gahadza Mega Market (Private) Limited, owned by Shiraan Ahmed, has moved to acquire 100 percent of Lobels Holdings (Private) Limited in a proposed transaction that could see one of…

Super El Niño: President urges caution

Joseph Madzimure and Precious Manomano FARMERS must prioritise early-maturing and drought-resistant crops for the 2026-2027 summer cropping season as Zimbabwe braces for a likely Super El Niño-induced dry spell, President…

Leave a Reply

Your email address will not be published. Required fields are marked *