THERE has been huge progress in the repair of cancer machines at Parirenyatwa Group of Hospitals with the Government announcing that the process was now 76 percent complete.
The Government also confirmed that the construction of 20 pharmacy stores is 90 percent complete while the repair of cancer machines is now 76 percent complete.
Speaking during the post-Cabinet briefing, Information, Publicity and Broadcasting Services Minister, Dr Jenfan Muswere said, the project is on course to achieve set targets.
“The construction of 20 pharmacy stores is 90 percent complete and the project is on course and is likely to achieve set targets within 100 days.
“The repair of cancer machines at Parirenyatwa Group of Hospitals is 76 percent complete.
“The Low Energy Unique machine is now working and has gone a long way in reducing the patient waiting list.”
Dr Muswere said that the installation of solar systems at 19 health facilities is 97 percent complete, with 14 facilities having been fully installed.
“The installation of the containerised laboratory at Sally Mugabe Hospital has been completed and the project is ready for commissioning.
“Construction of a water tank at Chitungwiza Hospital is still underway.”