Lubu Coal Project plant nears completion

Senior Business Reporter

Assembling of the wash plant at Lubu Coal Project in Hwange is now 75 percent complete, the mining firm has said.

The coal mine recently received key components of the plant.

In an update, the London Alternative Investment (AIM) listed miner -Contango Holdings said “Construction of our #CGO wash plant is now 75% complete. Upon completion, crushing and screening will also be installed.

“Following commissioning and optimisation it is expected to be able to produce 20,000 tonnes of washed coking coal per month,” said the mining house on its Twitter handle.

The firm plans to start production next month.

@nqobilebhebhe

Related Posts

Concern as women account for most new HIV cases in Beitbridge

Sukulwenkosi Dube-Matutu, [email protected] AUTHORITIES in Beitbridge have raised alarm over a surge in new HIV infections in the district, warning that the high proportion of females among those affected could…

ZimParks celebrates historic translocation of black rhinos to the shores of Lake Kariba

Fairness Moyana, [email protected] A group of critically endangered black rhinoceros has been reintroduced into Matusadona National Park in a landmark conservation achievement that marks the return of one of Zimbabwe’s…

Leave a Reply

Your email address will not be published. Required fields are marked *

×
×