Potraz to build 54 base stations

telecommunications become a basic need.
Potraz deputy director-general Mr Alfred Marisa said in an interview yesterday the authority has already erected 11 sites for the stations.
“The first phase (of the) project had eight terminal sites and three repeater sites while the second phase is targeting a total of 43 sites. Our target is to reach all under-served areas in Zimbabwe. The areas targeted and prioritised are remote rural areas,” he said.
Potraz has planned to roll out the project in two phases over two years, using resources from the Universal Services Fund. The first phase consisted of sites at Chidodo, Pfungwe, Neuso, Chilo, Chiodza, Malipati, Manama and Dhlamini. All the first phase sites are ready for radio frequency installations, with Chilo (Mahenye) and Malipati already on air. The other sites are awaiting the completion of microwave transmission installations, expected to be completed by the end of the month.
“Construction of towers at the 43 sites is likely to span over two years since the USF cannot fund all of them in one year, given that the USF is also funding other projects such as the Schools Connectivity project and some deserving postal projects,” said Mr Marisa.
Investment in infrastructure by operators since dollarisation and a slash in sim card prices improved access to mobile phones. Prior to dollarisation access to telecommunications, especially mobile, was limited to only a privileged few and was seen as a status symbol.
“As at the end of September 2012, the teledensity figure was 89,8 percent (active sim cards and fixed lines without factoring in multiple line ownership). Given the current growth trends, we expect teledensity to reach 100 percent by next year as mobile services are extended to more under-served rural areas,” Mr Marisa said.
The World Bank estimates that a 10 percent increase in teledensity raises a country’s Gross Domestic Product by at least 1 percent. Zimbabwe has three mobile phone operators — Econet Wireless, Telecel Zimbabwe and the State-owned operator NetOne. They all still fall short of covering the entire population.
It is against this background that Potraz seeks to ensure universal access to telecommunications through the installation of infrastructure in areas where operators would ordinarily not invest. To address gaps created by such a scenario, the postal and telecoms regulator has strongly advocated the sharing of infrastructure.
“Operators are already sharing infrastructure. Sharing infrastructure has been hampered by old designs (especially towers) which were originally not designed to carry more than one operator and, in some cases, inadequate backhaul infrastructure,” said Mr Marisa.

Related Posts

Super El Niño: President urges caution

Joseph Madzimure and Precious Manomano FARMERS must prioritise early-maturing and drought-resistant crops for the 2026-2027 summer cropping season as Zimbabwe braces for a likely Super El Niño-induced dry spell, President…

Manufacturing sector to hit US$1bn mark by 2030 — survey

Zvamaida Murwira Senior Reporter THE manufacturing sector is now the biggest contributor to the country’s Gross Domestic Product and is on course to reach a US$1 billion mark in exports…

Leave a Reply

Your email address will not be published. Required fields are marked *

×