Second Republic delivers: Chivhu Dam Profile

Capacity: 25 million cubic meters

River: Zibagwe

Catchment: Sanyati

Year mooted: 2005

Year Construction started: September 2018

Contractor: EG Construction

Implementing Agency: Zimbabwe National Water Authority

Completion Progress: 98,2 percent

Contract Value: US$41 526 919.76

Project Scope

l Construction of a 28,2m high earth-fill dam with a crest length of 346 metres and a 240 cubic meters per hour bulk water treatment plant together with a 7km pipeline linking the bulk water treatment works to the town’s water reticulation system.

l The project also included the establishment of a 120-hectare irrigation scheme.

Progress to date

l ZINWA already supplying water to Chivhu Town using the new, bigger and modern 240 cubic meters per hour water treatment plant

l Pipeline also complete

l 90 hectares of land under summer crop at the established irrigation scheme. The same irrigation scheme had a winter wheat crop last year.

l Dam has started impounding water

Outstanding works

l Works on the intake tower

Benefits of the dam

l Water for consumption in Chivhu Town

l Agriculture – up to 400ha of land would be irrigated using water from the dam

l Fisheries

l Tourism

l Power Generation

l Villagers resettled to pave way for dam construction also benefiting

l Livestock from nearby villages to get water too

Related Posts

Done & DUSTED . . . President signs Constitution of Zimbabwe Amendment (No. 3) Act (CAB3) into law

Zvamaida Murwira Senior Reporter President Mnangagwa has signed into law Constitution Amendment Bill Number 3, which, among other things, extends the presidential election cycle from five to seven years. The…

Govt adopts reintegration plan for returnees

Rumbidzayi Zinyuke Senior Reporter MORE than 78 000 Zimbabweans have returned home from South Africa in the wake of xenophobic attacks on foreigners in that country. This comes as more…

Leave a Reply

Your email address will not be published. Required fields are marked *

×
×