Second Republic Delivers: Kunzvi Dam Profile

Year Dam First Mooted: 1994

Type of Dam: A zoned earthfill embankment

Length: 2 600 metres

Height: 48,2 metres

Catchment: Nora and Nyaguwe rivers in Goromonzi

Initial Contract Value: US$108 million

Year Contract signed: 2021

Year Construction started: 2021

Expected Year of Commissioning: 2026

Contractor: China Nanchang Engineering

Implementing Agency: Zinwa

Progress to date

  • Excavation of main dam now 6 percent
  • Embankment placing of main dam 5 percent
  • Construction of site roads 35 percent
  • Site establishment is at 55 percent
  • Mobilisation at 85 percent

. Overall progress is 26 percent as of February 26, 2023

 

Benefits

  1. i) Harare, Chitungwiza and Ruwa water supply
  2. ii) Irrigation water for local communities

iii) Fisheries

  1. iv) Tourism
  2. v) Electricity generation
  3. vi) Livestock to get drinking water

Related Posts

Cassava Technologies partners Vodafone and Elsewedy Electric to form Africa Data Centres Egypt

Cassava Technologies, Vodafone Business and Elsewedy Electric have signed an agreement to establish Africa Data Centres Egypt, a data centre project that will include Egypt’s first sovereign AI data centre,…

VP Chiwenga meets China’s Vice Premier

Mukudzei Chingwere in BEIJING, China Zimbabwe’s investment and business engagements in China received high-level political impetus this afternoon after Vice President Dr Constantino Chiwenga met Chinese Vice Premier Ding Xuexiang…

Leave a Reply

Your email address will not be published. Required fields are marked *