Second Republic Delivers: Kunzvi Dam Profile

Year Dam First Mooted: 1994

Type of Dam: A zoned earthfill embankment

Length: 2 600 metres

Height: 48,2 metres

Catchment: Nora and Nyaguwe rivers in Goromonzi

Initial Contract Value: US$108 million

Year Contract signed: 2021

Year Construction started: 2021

Expected Year of Commissioning: 2026

Contractor: China Nanchang Engineering

Implementing Agency: Zinwa

Progress to date

  • Excavation of main dam now 6 percent
  • Embankment placing of main dam 5 percent
  • Construction of site roads 35 percent
  • Site establishment is at 55 percent
  • Mobilisation at 85 percent

. Overall progress is 26 percent as of February 26, 2023

 

Benefits

  1. i) Harare, Chitungwiza and Ruwa water supply
  2. ii) Irrigation water for local communities

iii) Fisheries

  1. iv) Tourism
  2. v) Electricity generation
  3. vi) Livestock to get drinking water

Related Posts

‘Our future is bright’ . . . We’ll soon be a global manufacturing hub: President

Zvamaida Murwira-Senior Reporter ZIMBABWE’S manufacturing sector will be an industrial hub for regional, continental and international markets as Government facilitates the implementation of its industrialisation agenda and accompanying institutional reforms,…

President reaffirms importance of strong Govt, Church ties

Debra Matabvu-Senior Reporter PRESIDENT MNANGAGWA has reaffirmed the importance of a strong partnership between the Government and the Church in promoting peace, national unity and socio-economic development. This followed a…

Leave a Reply

Your email address will not be published. Required fields are marked *

×