Second Republic delivers: Marovanyati Dam Profile

Owner: Government of Zimbabwe

Location: Buhera District, Manicaland Province. It is on Mwerahari River which has an annual flow of 182 million cubic metres

Year project was first proposed: 1971

Year contract was signed: May 2003

Year construction started: May 2003

Year construction stopped: It first stopped in May 2008 and stopped for the second time in June 2014 due to funding challenges

Year project was reviewed: August 2017 and Second Republic fast-tracked the construction 

Project cost: US$33 million which was internally generated

Contractor: China Jiangxi Corporation

Implementing Agency: Zimbabwe National Water Authority (Zinwa)

Dam type: Zone Earthfill

Gross capacity of lake: 50 million cubic metres

Surface area: 546 hectares

Maximum dam height: 35 metres

Maximum water depth: 28,2 metres

Dam wall crest length: 470 metres

Spillway length: 120 metres 

Construction status: Dam construction is complete and was commissioned by President Mnangagwa on November 11, 2020

Catchment: Save River

Benefits

λ Murambinda water supply. The dam is located 7km west from Murambinda Growth Point  

λ  Agriculture – Murambinda is in Ecological Region 5, and 85 percent of crops this season were written off due to prolonged drought

λ  Dam will support irrigation on 1 250 hectares and boost peoples’ incomes. 

λ  Under first phase, two irrigation schemes – Guwanda 100 hectares and Kwarire 400 hectares – are being prioritised this year 

λ Fisheries will generate incomes too and improve nutrition 

λ Tourism – boat cruising, keeping wildlife are planned

λ Power generation

λ  Dorowa mine will get water from Marovanyati Dam

λ  Employment creation on irrigated farms, tourism sector, etc. — Compiled by Africa Moyo

Related Posts

President declares September 15 a public holiday

Gibson Nyikadzino Zimpapers Politics Hub PRESIDENT Mnangagwa has declared September 15 a public holiday. In a proclamation through Statutory Instrument 148 of 2026, read in terms of Section 2 (2)…

Cassava Technologies partners Vodafone and Elsewedy Electric to form Africa Data Centres Egypt

Cassava Technologies, Vodafone Business and Elsewedy Electric have signed an agreement to establish Africa Data Centres Egypt, a data centre project that will include Egypt’s first sovereign AI data centre,…

Leave a Reply

Your email address will not be published. Required fields are marked *