Second Republic delivers: Silverstroom Dam

Year Mooted: 1974

Province: Mashonaland Central

Year contract signed: 2020

Year construction started: 2020

First contract value 2020: US$164 258 525

Contractor: China Nanchang

Implementing Agency: Zimbabwe National Water Authority

Scope of works:

  • Construction of a 70-metre-high double curvature concrete dam
  • Care and diversion of the river
  • 102m drop inlet spillway
  • Outlet works and access road
  • Construction of bulk treatment works and pipeline

Progress so far

  • Engineer’s site establishment now at 60 percent
  • Contractor’s Site establishment now at 85 percent
  • Temporary access road No.1 construction now 100 percent
  • Temporary access road No.2 construction – 90 percent

Overall progress: 12 percent

Benefits of the dam

  • Centenary water supply
  • Agriculture – Irrigation of up to 2 400 hectares
  • Fisheries
  • Tourism
  • Power generation of up to 800 kilowatts

Related Posts

President declares September 15 a public holiday

Gibson Nyikadzino Zimpapers Politics Hub PRESIDENT Mnangagwa has declared September 15 a public holiday. In a proclamation through Statutory Instrument 148 of 2026, read in terms of Section 2 (2)…

Cassava Technologies partners Vodafone and Elsewedy Electric to form Africa Data Centres Egypt

Cassava Technologies, Vodafone Business and Elsewedy Electric have signed an agreement to establish Africa Data Centres Egypt, a data centre project that will include Egypt’s first sovereign AI data centre,…

Leave a Reply

Your email address will not be published. Required fields are marked *