Second Republic delivers: Tuli-Manyange Dam profile

River:  Tuli

Province: Matabeleland South

District:  Gwanda 

Type of dam: Cylindrical Arch Concrete Dam

Volume of concrete: 61 000 m3

Spillway: Simple overflow ogee

Catchment area: 5 770 km2

Full supply capacity: 33 million cubic metres

Contract Value: US$87 298 435.17

Year Mooted: 1995

Year construction started: 2006

Year Construction stopped: 2006

Year Construction resumed: 2021

Expected Date of completion: December 2023

Overall progress: 35 percent

Contractor: China International Water and Electric Corporation

Implementing Agency: Zimbabwe National Water Authority

Progress to date

— Coffer dam now complete and providing water to the construction site and surrounding communities.

— Saddle Dam 1 is 80 percent complete

— Concrete batching plant is now fully installed

— Main dam foundations excavations now 70 percent complete

Benefits

— Irrigation: to support 1 200 hectares, boosting food security in Matabeleland South. Areas to benefit include Vela, Guyu Business Centre, Ntalale Business Centre, Chelesa Business Centre, Sizhubane Barracks, Manana Mission and Business Centre, Sebasa and Mankonkoni irrigation schemes 

— Water supply to communities that are presently facing water challenges 

— Livestock from nearby communities to get water

Related Posts

Zim earns respect of nations, businesspeople

Mukudzei Chingwere Senior Reporter ZIMBABWE’S independent foreign policy and willingness to speak its mind on global affairs are earning the country growing respect among the comity of nations and on…

Harness tech for industrialisation, says President . . . AI-driven beneficiation the way to go

Wallace Ruzvidzo in NEW YORK, USA ZIMBABWE hogged the limelight at the United Nations on Thursday, with Vice-President of the 81st Session of the UN General Assembly and Permanent Representative…

Leave a Reply

Your email address will not be published. Required fields are marked *

×