Second Republic delivers: Ziminya Dam profile

Province: Matabeleland North

District: Nkayi

Catchment: Gwayi

Capacity: 98 million cubic meters

Contractor:   Fossil Contracting

Implementing Agency: Zimbabwe National Water Authority

Year Mooted: 1998

Year Construction Started: 2021

Project Cost:  US$132 152 526,72

Progress so far

  • Dam Site Survey at 75 percent
  • Embankment foundation excavation 63 percent
  • Access road at 65 percent
  • Dam foundation clearing 95 percent
  • Coffer Dam at 65 percent
  • Dam foundation clearing 95 percent

Overall Progress: 16 percent

Benefits

— Completion of Ziminya Dam will open the path for the growth and expansion of Nkayi

— It will lead to the opening up of 1 250 hectares of irrigated land in the area.

— This will go a long way in the transformation of livelihoods in Nkayi

— Irrigation will help improve food security for surrounding communities, and lead to improved standards of living for people

— The dam will bolster water supplies to Nkayi Centre.

— The dam project also includes the construction of a bigger and modern water treatment plant.

— Fisheries ventures will be undertaken

— Power generation will also be done using water from the dam

— Recreational activities will be undertaken on completion

Related Posts

President declares September 15 a public holiday

Gibson Nyikadzino Zimpapers Politics Hub PRESIDENT Mnangagwa has declared September 15 a public holiday. In a proclamation through Statutory Instrument 148 of 2026, read in terms of Section 2 (2)…

Cassava Technologies partners Vodafone and Elsewedy Electric to form Africa Data Centres Egypt

Cassava Technologies, Vodafone Business and Elsewedy Electric have signed an agreement to establish Africa Data Centres Egypt, a data centre project that will include Egypt’s first sovereign AI data centre,…

Leave a Reply

Your email address will not be published. Required fields are marked *