Zinara has disbursed over ZWG7,17 billion to road authorities

Freeman Razemba

Senior Reporter

THE Zimbabwe National Road Administration has so far disbursed over ZWG 7,17 billion to road authorities countrywide for infrastructure development and maintenance.

This was revealed in its latest disbursement report.

According to Zinara, works funded include upgrading roads to bitumen standards, rehabilitation, resealing, gravelling, motorised grading, drainage structures and carriageway markings among other works.

“ZINARA has disbursed approximately ZWG7,17 billion against its approved 2026 budget of ZWG9,8 billion as at September 30, 2026,” it said.

“This accounts for 73 percent budget utilisation, leaving ZWG2.6 billion for disbursement. Budget utilisation and funding trend; Quarterly disbursements stood at ZWG2.099 billion in Quarter 1, ZWG2.531 billion in Q2 and ZWG2.540 billion in Q3, demonstrating consistent funding momentum through the year.

“The 2026 trajectory reflects improved disbursement pacing, with Q3 2026 alone (ZWG2,54 billion) nearly matching the entire H1 2025 outturn.”

The authority said on road network delivery, against an annual target of 40 059km of road rehabilitation and maintenance, 31,602km had been achieved by the end of September, which is 79 percent of the annual target.

“Works funded include upgrading roads to bitumen standards, rehabilitation, resealing, gravelling, motorised grading, drainage structures and carriageway markings, among other works,” it said.

“This performance builds on the 2025 programme, as the Department of Roads and RIDA accessed their full allocations of ZWG421.39 and ZWG243.24 million respectively.

“Some of the roads that have been attended to date include the 97km Nyanga-Rusape Road in Manicaland where routine maintenance was done, South Hill-Matekenya in Gwanda where motorised grading was done on 32km, and 27km of spot gravelling on Chakonda-Madziwa Township Road among other roads in various provinces.”

Zinara said provincial budget utilisation continues to steadily grow, with provinces at various levels of uptake, mostly driven by the various procurement stages for capital projects that the Authorities are undertaking. Mashonaland East recorded the highest utilisation at 80 percent, receiving ZWG31.44 million against an allocation of ZWG39.38 million.

Mashonaland West followed at 70 percent with Mashonaland Central at 62 percent and Midlands at 61 percent.

Manicaland recorded 56 percent; Harare and Bulawayo metropolitan provinces each stood at 41 percent while Masvingo recorded 38 percent, Matabeleland South 37 percent and Matabeleland North 34 percent.

“Collectively, provincial allocations recorded 52 percent utilisation. Beyond road works funding, ZINARA continues to support Road Authority capacitation. Several Road Authorities have committed funds to equipment procurement to reduce reliance on external contractors. “Although disbursement records show 11 Road Authorities had not accessed funds since the start of the year, this does not reflect exclusion from funding; rather, allocations are committed to equipment procurement, with disbursements scheduled on delivery.”

The authority said this mirrors the 2025 experience, where the 2025 disbursement report noted that certain Road Authorities had funds committed to equipment procurement, with disbursements to follow upon delivery.

As the 2026 financial year draws to a close, ZINARA said it will maintain its focus on enhancing revenue mobilisation and directing resources towards road maintenance, rehabilitation and Road Authority operational capacity.

“Management projects an acceleration in disbursement uptake in Quarter 4, with the remaining ZWG2.6 billion expected to be deployed to close the year at full budget utilization,” he said.

“With a number of key projects still ongoing across the country, ZINARA remains committed to ensuring that resources are fully availed and that delivery progress is achieved in line with the annual programme.”

 

 