Disco Manhize plant temporarily shut down

Patrick Chitumba, [email protected] 

THE Dinson Iron and Steel Company (Disco) Manhize plant will be temporarily shut down to facilitate routine repair and maintenance between now to November, management has said. 

The move is necessary for several reasons, which include scheduled maintenance of critical plant equipment, Dinson group public relations manager, Mr Joseph Shoko, said in an interview yesterday. 

“The Dinson Iron and Steel Company Manhize Steel plant will be undergoing a temporary repair and maintenance shutdown from September 11, 2025, to November 11, 2025,” he said. 

“The plant is due for routine maintenance to ensure optimal performance and prevent unexpected breakdowns. This maintenance window allows for inspection, repair, and replacement of critical equipment, minimising future disruptions.” 

Mr Shoko said during the shutdown period, engineers will also do equipment test run and commissioning. 

“Most plant equipment is still under test run, and the shutdown provides an opportunity to complete the commissioning process,” he added. 

“Test runs are essential to verify that equipment functions correctly and efficiently, identifying potential issues before full production begins. 

“This process ensures that all systems operate as intended, reducing the risk of costly repairs and downtime.”

Mr Shoko said there was also a major breakdown at the Sintering plant that called for the immediate plant maintenance. 

“A significant breakdown at the sintering plant, a critical component of iron and steel production, requires immediate repairs to prevent further damage and ensure a safe working environment,” he said. 

The company has reiterated the importance of test runs that include verifying equipment functionality and performance, identifying potential issues before full production, reducing risk of costly repairs and downtime while ensuring safe and efficient operation.

“During the shutdown, all employees will receive their salaries, and a formal works council meeting was held to discuss the temporary shutdown in a transparent and harmonious manner,” said Mr Shoko. “Employees were advised through their workers committee, and the human resources department will handle formalities before the shutdown. All employees are expected to report for duty on November 12, 2025,” he explained. 

Mr Shoko said the temporary shutdown is a normal part of plant maintenance, ensuring the safe and efficient operation of the facility. 

“By completing these repairs and maintenance tasks, the plant can minimise future disruptions and optimise production. By completing these repairs and maintenance tasks, the plant can minimise future disruptions and optimise production,” said Mr Shoko.

 

 

 

Related Posts

Chiefs told to safeguard independence of community courts

Patrick Chitumba [email protected] TRADITIONAL leaders have been urged to uphold judicial independence, integrity and fairness in the administration of justice, with chiefs challenged to ensure community courts remain free from…

Legal showdown looms as developer rejects Beitbridge council contract termination

Thupeyo Muleya, Beitbridge Bureau A LEGAL showdown is looming between the Municipality of Beitbridge and land developer Kingdom Lifestyle Africa (Private) Limited after the company rejected the local authority’s decision…

Leave a Reply

Your email address will not be published. Required fields are marked *