Kazungula bridge complete

Gaborone. — Package one of the Kazungula bridge project, comprising the bridge proper and approach ramps, is complete, according to a media release from the Ministry of Transport and Communications.

The release says the bridge, whose construction commenced in 2014 at a contract sum of approximately P1 994 950 041.44 (US$174 184 799.54) was 100 percent complete.

It says package two, being a Botswana one stop border post, currently under construction at a cost of P440 116 275.30, was at 98.44 percent with completion expected end of this month.

Package three, the Zambia one stop border post, ongoing at a contract sum of about P150 441 669.48 (ZMW 263 670 419.98), was at 99.40 percent. — BOPA.

Related Posts

‘Munhumutapa legacy informs the present’ . . . Courage, innovation, hard work and self-determination our key attributes

Nyore Madzianike-Senior Reporter The rich history of the great Munhumutapa Empire symbolises Zimbabwe’s identity and capacity to govern itself, with the Second Republic mirroring the administration and organisational structures of…

Do your best always, President rallies youth

Joseph Madzimure-Zimpapers Reporter President Mnangagwa has called upon the youth never to  settle for average, but to work hard and make clean money, following in the footsteps of the innovative…

Leave a Reply

Your email address will not be published. Required fields are marked *