Lack of funding, brain drain stalls Nust construction projects

LACK of funding and brain drain has stalled construction projects at the National University of Science and Technology (Nust) in Bulawayo, an official has said.

Pro Vice-Chancellor, Dr William Goriwondo, confirmed that the the institution was failing to complete a number of construction projects due to financial constraints and the flight of skilled personnel in search of greener pastures.

Nust embarked on massive construction projects which include a Technovation Centre and an Information Technology (IT) resource centre, which is sitting at 30 percent completion.

Construction of residential blocks for Chemical Engineering and Applied Science students has also stalled due to a lack of funding.

The Technovation Centre, whose construction began in 1998 and stalled in 2008 due to financial constraints, was designed as a campus service centre  but  was repurposed due to the thrust of the Education 5.0 policy into an innovation centre.

 

“The challenge we are facing now is staff and skills shortage mainly as a result of brain drain. We have a situation where we have to receive assistance from our sister Government institutions and departments,” said Dr Goriwondo. 

He said the army was assisting with specialised skills and Bulawayo Polytechnic was also supporting the university on the technical aspect,.

Dr Goriwondo however said there was a need to pay allowances to skilled workers in order to attract and retain them. He urged vocational training centres and polytechnic colleges to continuously upgrade the training of artisans to ensure they meet the needs of the market.

Dr Goriwondo also appealed for supplementary Public Sector Investment Programme (PSIP) funding to enable the institution to complete outstanding works as well as to start new ones.

He said instability in the prices of materials and failure by suppliers to deliver complete consignments also affected progress.

“Instability in prices of material is affecting us greatly. The model being used by suppliers and contractors is that they do forward pricing knowing that the payment will come late. This has impacted on progress on the projects,” he said. — New Ziana.

Related Posts

Mother of three sets of twins relocates to Tsholotsho

Mthokozisi Ncube [email protected] A MOTHER of three sets of twins, Zobuhle Ndlovu, and her six children have finally relocated to Tsholotsho after receiving assistance from well-wishers following the publication of…

Mbende dance takes centre stage at Mash East Chibuku Neshamwari provincial finals

Mthabisi Tshuma Zimpapers Arts and Entertainment Hub The iconic Mbende Jerusarema dance is set to dominate proceedings at the Mashonaland East Chibuku Neshamwari Traditional Dance provincial finals, taking place on…

Leave a Reply

Your email address will not be published. Required fields are marked *

×
×