Road upgrade in limbo

Conrad Mupesa

Mashonaland West Bureau

The rehabilitation of the 60km Alaska-Copper Queen Road that commenced in 2018, is yet to gather pace after this year’s works were suspended due to the Covid-19 pandemic.

The road links Mashonaland West and Midlands Province’s Gokwe North District.

It also shortens the distance from Harare to Gokwe. The Ministry of Transport and Infrastructural Development was allocated US$7 million for the first 10 km stretch,US$3 million and an additional $12 million.

Mashonaland West Province’s resident engineer in the Ministry of Transport, Engineer Simbarashe Gomo, said Covid-19 stalled the road’s upgrade.

“We had set up a target of completing 5km of the first 10km stretch in July for five months, but, the nation was forced to divert some of its financial resources to battle the pandemic.

“Our target was also to work on other critical areas along the entire road including bridges,” he said.

 

Related Posts

President challenges youth: Work hard, make money

Farai Dauramanzi Echo Editor PRESIDENT Mnangagwa has reinforced Government’s commitment to building a stronger, modernised and industrialised Zimbabwe that leaves no one behind. Addressing thousands of people gathered for the…

Nyamhuri claims maiden ODI five wickets … as Australia sets Zimbabwe 295

Don Makanyanga Online Writer Zimbabwe fast bowler Newman Nyamhuri claimed his maiden five-wicket haul in One-Day International cricket as Australia posted 294 for eight in their allotted 50 overs, setting…

Leave a Reply

Your email address will not be published. Required fields are marked *