Second Republic delivers: Bindura Dam profile

Capacity: 100 million cubic meters

Year Mooted: 1986

Year Contract signed: 2005

Year Construction started: 2005

Year Construction Stopped: 2008

Year Construction Resumed: 2018

Contract Value: US$132 384 085. 50

Contractor: China Jiangxi International Technical and Economic Corporation

Implementing Agency: Zimbabwe National Water Authority 

Progress to date

• Engineer’s site establishment is at 90 percent 

• Contractor`s site establishment is at 95 percent 

• Clearing and stripping on the main dam core trench is at 90 percent 

• Excavations on the inlet and outlet section is at 70 percent 

• Opening of borrow areas (clearing and stripping) is at 6 percent 

• Construction of coffer dam is at 85 percent 

• Drilling and blasting for the cut-off (main dam) is at 75 percent  

Overall Progress: 38 percent 

Scope of works

• Construction of a conventional earth-fill dam with a height of 44 metres

• Three saddle dams

• 150-metre long spillway

• Bulk water treatment works and pipeline

Benefits

• Bindura water supply

• Irrigation (2 500 hectares)

• Fisheries

• Tourism

•Water for livestock and other communal needs

Related Posts

‘Our future is bright’ . . . We’ll soon be a global manufacturing hub: President

Zvamaida Murwira-Senior Reporter ZIMBABWE’S manufacturing sector will be an industrial hub for regional, continental and international markets as Government facilitates the implementation of its industrialisation agenda and accompanying institutional reforms,…

President reaffirms importance of strong Govt, Church ties

Debra Matabvu-Senior Reporter PRESIDENT MNANGAGWA has reaffirmed the importance of a strong partnership between the Government and the Church in promoting peace, national unity and socio-economic development. This followed a…

Leave a Reply

Your email address will not be published. Required fields are marked *

×