Zesa loses 1 282 transformers to vandalism

Enacy Mapakame Business Reporter

State power utility Zesa Holdings has lost 1 282 transformers worth nearly US$500 million in the past five years due to vandalism in what the Government says tantamounts to acts of sabotage.

This has worsened power supply distribution in the country for both businesses and household consumers.

In 2021 alone, the power utility lost 288 transformers plunging many into darkness. This was against a production of only 281 transformers during the same year.

Energy and Energy Infrastructure Deputy Minister Magna Mudyiwa said cases of vandalism remained one of the major challenges affecting power supply in the country, at a time demand is rising due to increased economic activity against reduced production capacity at the main power producing stations in Kariba and Hwange.

“Top of the challenges affecting power supply in the country is the issue of vandalism and this is taking us backwards. Last year a total of 288 transformers were lost.

“From January 2017 to 2022, Zesa lost 1 282 transformers to vandalism and these are worth US$495 million. This is 10 times the replacement value.

“I think these criminals have since moved from just vandalism to total sabotage. Zesa is now losing more transformers than they can replace.

“So you can see how vandalism is slowing down production of the much needed electricity,” she said. She was speaking during the Global Renaissance Investments (GRI) Zimbabwe Infrastructure Investment Summit held in Victoria Falls.

She added the power utility was facing a multitude of other challenges such as old equipment at its power generation plants in Hwange as well as the smaller thermal units in Bulawayo, Harare and Munyati.

Hwange is currently producing an average 400MW against a capacity of 900MW due to old equipment.

“At Hwange for instance, the equipment is now obsolete and can hardly operate at full capacity. Out of the six units, we operate about four or three units sometimes, which is reducing power supplies,” she said, adding climate change had also become a menace and constantly reduced water levels at Kariba dam.

The Deputy Minister however indicated the country has vast opportunities for increased energy generation with works already underway to increase power generation at Hwange.

This is in addition to other smaller generation projects in the pipeline at some of the country’s large water bodies and rivers such as Pungwe and Tugwi Mukosi which will be expected to add about 15MW into the national grid as well as at Late Mutirikwi which will generate 5MW.

“We also have a lot of opportunities for renewable energy such as solar, we have an abundance of sunshine suitable for power generation,” she said.

Related Posts

Road crashes: President reads riot act

Debra Matabvu-Senior Reporter PRESIDENT Mnangagwa has issued a directive mandating all Government departments and agencies to urgently implement sweeping measures to curb reckless and irresponsible road user behaviour while also…

President declares rivers state of disaster

Zvamaida Murwira-Senior Reporter PRESIDENT Mnangagwa has declared a state of disaster for at least 17 rivers following years of degradation linked to mining activities. The declaration, formalised in a Statutory…

Leave a Reply

Your email address will not be published. Required fields are marked *

×
×