Bulawayo-Victoria Falls Highway rehabilitation takes off

Rutendo Nyeve Victoria Falls Reporter 

FIVE local contractors have moved in to lead the rehabilitation of the Bulawayo-Victoria Falls highway, with significant progress already made in clearing detour paths to keep traffic flowing during construction.

The Ministry of Transport and Infrastructural Development on Thursday named Fossil Contracting, Masimba Construction, Syvern Investment, Bitumen Resources, and Tensor Systems as the firms driving the critical infrastructure project, divided into five lots along the key route.

In an update on Thursday, the Ministry confirmed all contractors are now on-site and actively working, with bush clearing for detours already completed along multiple sections of the highway.

 

“Fossil Contracting (Lot 1) has 4km detour cleared from 48.6km peg, Masimba Construction (Lot 2) has cleared 5km between 85km-90km pegs, Syvern Investment (Lot 3) has cleared 5km (99.6km-104km) with more underway,

Bitumen Resources (Lot 4) has cleared 4.2km from 201.6km toward 191km and Tensor Systems (Lot 5) has cleared 5km between 201.6km-211.6km pegs

“The rehabilitation is progressing well with all contractors now operational on their designated sections,” said the Ministry.

The Ministry said the detour system serves three key purposes that include ensuring worker and motorist safety, maintaining construction efficiency and guaranteeing long-term road quality.

Mtorists have been urged to strictly observe all temporary signage and reduce speeds when approaching work zones.
The 350km highway, a vital tourism and trade corridor, is expected to see dramatically improved travel conditions upon completion of the upgrade.
@nyeve14

Related Posts

No one will lose property:Ziyambi . . . as Government pegs validation fee at US$215

Trust Freddy, Zimpapers Correspondent CITIZENS who fail to validate their property documents within the prescribed 24-month deadline will not forfeit their ownership rights, as unvalidated paper deeds remain legally sound,…

New High Court judges challenged to deliver faster justice

Patrick Chitumba, [email protected] THE 15 newly appointed High Court judges have been challenged to hit the ground running and turn the country’s biggest-ever simultaneous expansion of the High Court Bench…

Leave a Reply

Your email address will not be published. Required fields are marked *