Heavy rains disrupt mining operations

Victoria Falls Reporter
HEAVY rains have disrupted coal mining activities in Hwange district where about 90,000 tonnes of coal peas at Makomo Resources meant for electricity generation are submerged in water.
The development resulted in a coal deficit in two small thermal power stations in Bulawayo and Munyati, which rely on supplies from the company.

Makomo Resources general manager, Samson Mabvira, said the Zimbabwe Power Company requested the mine to supply coal peas to Bulawayo and Munyati Thermal Power stations but their efforts had been derailed by the rains as most of the coal peas were under water.

“We understand that stocks at Bulawayo and Munyati are low. The problem has been the rains because most of the peas are under water,” he said.

“So we need to de-water the pits and dry the peas hopefully by weekend and normal supplies to the thermal power stations will resume.”
Mabvira said coal peas production was also linked to power generation at Hwange Thermal Power Station where output was also depressed.

“To access low ash coal, Hwange Power Station has to be mined out first. At the moment Makomo Resources is stockpiling this coal due to depressed off take,” he said.

Bulawayo and Munyati power stations consume about 300 tonnes of coal peas a day and need about 9,000 tonnes per month each.

Related Posts

Spirit of ubuntu. . .‘Zimbabwe ready for ICC World Cup showpiece’

Petros Kausiyo in Johannesburg, South Africa SOUTHERN Africa’s host nations rolled out the red carpet for the 2027 ICC Men’s Cricket World Cup with the Minister of Sport, Recreation, Arts…

Marula tobacco farmer leads diversification model with thriving horticulture project

Raymond Jaravaza, [email protected] FOR tobacco farmer Mr Sola Reed of Marula in Matabeleland South Province, successful farming requires planning beyond a single crop, with diversification forming part of his agribusiness…

Leave a Reply

Your email address will not be published. Required fields are marked *

×