‘Kariba Dam rehabilitation project now 80pc complete’

THE US$294,2 million rehabilitation project of the Kariba Dam wall is now 80 percent complete, the Zambezi River Authority (ZRA) said Wednesday.

Comprising three components — the reshaping of the plunge pool, refurbishment of the spillway upstream control facility and institutional strengthening — the rehabilitation is projected to be completed by the first quarter of 2025, according to the ZRA, a bi-national organisation managing the dam on behalf of the governments of Zambia and Zimbabwe.

“Upon completion, the Kariba Dam Rehabilitation Project (KDRP) will be recorded in history as the first project of this magnitude ever undertaken with open-pit excavation at the foot of a 60-year-old dam with underground powerhouses on either bank of the river in full operation.

“To date, the overall project (including the Spillway Refurbishment sub-project) is about 80 percent complete,” said ZRA chief executive Engineer Munyaradzi Munodawafa.

According to the ZRA, the overall objective of the KDRP is to address dam safety concerns and restore the structural integrity of the dam for its long-term reliability and safety of operation.

Shared by Zimbabwe and Zambia, Kariba Dam supplies water to Zambia’s 1 080 megawatts (MW) North Bank Power Station and Zimbabwe’s 1 050 MW South Bank Power Station, also known as the Kariba Hydro Power Station.

The two power stations have in recent years been upgraded by Chinese firm Sinohydro, which has added 360MW to the North Bank Power Station and 300MW to Kariba Power Station. – Xinhua

 

Related Posts

President hailed for swift action on river degradation

Online Reporter President Mnangagwa has been hailed for unveiling a sweeping emergency rehabilitation programme targeting rivers damaged by illegal and destructive alluvial mining. Agriculture, Mechanisation and Water Resources Development Minister,…

NEW: President warns against irresponsible driving, unroadworthy vehicles

Harmony Agere PRESIDENT MNANGAGWA has warned against irresponsible driving and the use of unroadworthy vehicles following a series of fatal road traffic accidents recorded across the country in recent days.…

Leave a Reply

Your email address will not be published. Required fields are marked *

×
×