Mbudzi interchange: 11 out of 15 bridges complete

The Herald- ELEVEN of the 15 bridges needed for the Mbudzi Interchange in south Harare are now complete and the Masvingo-Glen Norah loop road is set to be open to traffic anytime soon.

The design for the Mbudzi interchange is made up of 15 bridges, with 13 directly on the interchange, while two bridges are each on Amalinda Drive and Harare Drive.

Yesterday, The Herald established that the main interchange is now almost complete, with just two bridges left. Some of the outstanding works include installation of the beams already on site.

The interchange is being built at the intersection of Simon Mazorodze Road, Chitungwiza Road and High Glen Road.

Related Posts

Slain commissioner’s Midlands State University lover exposed

Arron Nyamayaro THE woman, whose long-term extra-marital affair with MSU lecturer Martin Muduva, triggered a sequence of tragic events in Dzivarasekwa yesterday, has been identified as Patience Mangwiro. She is…

Roora Day for husband and lover was the last straw for nurse who axed hubby and downed rat poison

. . . Her friend says Lyliosa had been tormented by her husband’s extra-marital affair for years Arron Nyamayaro THE nurse who axed her husband THREE times, in a brutal…

Leave a Reply

Your email address will not be published. Required fields are marked *