ZPC working around the clock to restore power supply

Ivan Zhakata

Herald Correspondent

The Zimbabwe Power Company (ZPC) is working tirelessly to restore electricity supply following two major incidents that struck the nation’s power infrastructure on Sunday, 4 May 2025.

Engineers and technicians have since been deployed nationwide in a coordinated effort to stabilise the grid and bring relief to affected communities.

The first incident occurred at Hwange Power Station, the country’s largest thermal power plant, which lost Unit 2 due to a boiler tube leak.

At the same time, abnormal water chemistry was detected, pointing to acidic contamination within the system.

“The water treatment plant was immediately identified as the source,” ZPC said in a statement.

“Our teams acted swiftly to isolate the affected systems and flush out the contaminants. Water supply has since been stabilised to support plant operations.”

Despite the setback, ZPC engineers wasted no time initiating repairs.

Units 1 and 2, which sustained significant tube damage, are currently undergoing restoration, while pressure testing continues on Units 3, 4 and 6.

According to ZPC, Unit 1 is expected to be back online by the early hours of Wednesday, 7 May, with the remaining affected units targeted for full recovery by Friday, 9 May.

“Hwange is a key part of the national grid, and our personnel have been working tirelessly, day and night, to get it back to full capacity,” the company said.

However, as restoration work intensified in Hwange, there was another development.

A fire engulfed Highfield Substation in Harare around 8 pm, damaging a 20MVA transformer, key circuit breakers, current transformers and essential control cables.

The incident disrupted power to several areas, including Southerton, Workington, Willowvale, Highfield, Glen Norah and parts of Mbare.

Undeterred, ZPC and ZETDC teams immediately launched emergency response operations.

Power rerouting and load reconfiguration were swiftly implemented.

Workington is now being temporarily backfed from Kambuzuma, while Willowvale is receiving power through Parkridge via Glen View.

A transformer is being relocated from Hatgates to replace the one lost in the fire.

Related Posts

IMF impressed by Zim economy . . . meets all end-March targets . . . rating boon for economy

Nqobile Bhebhe-Zimpapers Business Hub ZIMBABWE has reached another significant milestone in its economic reform and international re-engagement drive after the International Monetary Fund (IMF) Management approved the completion of the…

Govt to pursue pensions, benefits for SA returnees

Zvamaida Murwira-Senior Reporter GOVERNMENT will engage South African authorities over unpaid benefits and pensions for Zimbabwean returnees under the ongoing repatriation exercise. Speaking to journalists at a post-Cabinet media briefing,…

Leave a Reply

Your email address will not be published. Required fields are marked *

×