Sikhumbuzo Moyo, [email protected]
MATABELELAND is among the beneficiaries of Government’s Second 100-Day Cycle development programme, with key projects targeting housing, judicial infrastructure and improved access to public services as the Second Republic accelerates implementation of its development agenda.
The projects also extend to previously underserved communities, reflecting Government’s efforts to ensure that development reaches areas that have historically lagged in infrastructure provision and service delivery.
According to this week’s Cabinet report, 27 projects were being implemented in Binga, Tsholotsho and Nkayi in Matabeleland North, as well as Mwenezi, Mlambapele in Gwanda, Gokwe, Mbire, Siakobvu and Kanyemba.
“Of the 27 projects in these areas, 15 have achieved implementation levels of between 80 and 100 percent, while 10 were between 61 and 79 percent. Only two projects are below target,” Information,
Publicity and Broadcasting Services Minister, Dr Zhemu Soda, said.
The targeted interventions are intended to improve access to essential services and stimulate development in communities that have traditionally faced infrastructure and service delivery challenges.
Projects benefiting the region include the new Gwanda Court Complex, the Duplex/Garden Flats housing project in Beitbridge, Matabeleland South, and the Rangemore Phase Two Housing Project in Bulawayo.
The projects form part of 211 programmes and initiatives being implemented by 27 Government ministries, departments and agencies under the National Development Strategy 2 (NDS2), covering the period 2026 to 2030.
In his Post-Cabinet briefing on Tuesday, Dr Soda said 136 of the 211 projects had achieved between 80 and 100 percent of their targeted implementation milestones, representing 64,5 percent of the total.
“A further 45 projects were within the 61 to 79 percent completion range, while 30 were below target, having achieved 40 percent or less of their intended implementation milestones,” he said.
The Second 100-Day Cycle ran from May 25 to September 1, 2026, with Government prioritising high-impact, citizen-centred projects that could be implemented within a relatively short period.
The Gwanda Court Complex is expected to strengthen access to justice through improved facilities for the administration of justice, while the Beitbridge and Rangemore housing developments will contribute towards expanding accommodation infrastructure in urban centres.
Nationally, several major projects were completed and commissioned during the review period, including the Manyame and Mucheke River bridges along the Harare-Masvingo-Beitbridge Road.
Other completed projects include the Sable Chemical Plant in Kwekwe, with a production capacity of 240 000 metric tonnes, a nurses’ home at Parirenyatwa Group of Hospitals and the installation of CT scanners at Chitungwiza and Sally Mugabe hospitals.
Government also completed the construction of male and female police barracks at Siyakobvu Police Station in Kariba District, Mashonaland West Province.
Dr Soda said implementing projects across the country was reinforcing the devolution and decentralisation agenda by empowering lower tiers of Government to coordinate and implement development initiatives in their respective areas.
The Second 100-Day Cycle is part of Government’s broader strategy to translate NDS2 targets into measurable interventions, with infrastructure development, economic growth and improved access to public services among its key priorities.